Applying for an extension of the building permit for the construction of an installation Unternehmensstart und Gewerbezulassung Anlagen, Waren und Stoffe

You can apply for a one-off extension of the building permit for up to two years if you have a valid building permit for your construction project.

  • Basic information

    If you have a valid building permit for your building project, you can apply for an extension of the building permit.

    The competent lower building supervisory authority can extend the building permit once for up to 2 years if the legal requirements have not changed in the meantime and the application has been received by the competent lower building supervisory authority before the deadline expires.

    Requirements

    The requirements for a one-off extension of two years are

    • the existence of a valid building permit,
    • compliance with the extension period of three years since the building permit was issued,
    • the documents submitted in accordance with § 3 of the Bremen Building Submission Ordinance remain valid,
    • the legal requirements have not changed in the meantime and
    • the application has been received by the competent lower building supervisory authority before the expiry of the deadline.
  • Procedure

    Apply for the extension in writing (informally). Indicate which building permit your application for extension relates to. Submit the application to the responsible lower building supervisory authority.

    The lower building supervisory authority will examine your application and involve those bodies whose participation or consultation is required for the decision on the building permit or without whose opinion the application cannot be assessed. You will then receive an extension of the building permit, provided the requirements for this are met.

    The extension of the building permit is subject to a fee. You will receive a notification of fees. If necessary, the lower building supervisory authority will ask you to make an advance fee payment as soon as you submit your application.

  • Competent Department

  • Fees / Costs

    The amount of the fee is based on § 1 of the Construction Costs Ordinance, tariff number 101.08.

  • Deadlines & processing time

    What deadlines must be paid attention to?

    During the term of the building permit, the building permit can be extended once for up to two years.

    How long does it take to process

    The lower building supervisory authority should decide on the extension of the building permit within twelve weeks after the completeness of the application has been confirmed in accordance with Section 69 (3) of the Bremen State Building Code.

  • Legal Bases

  • More Information

Feedback on quality

Your feedback will help us to identify and solve problems. You will not receive a personal response. Please do not submit any personal data.

Did you find what you were looking for?

How do you rate this page?*

*Mandatory field

This page has been automatically translated by DeepL. We cannot guarantee that the translation is correct.

The official information in German is complete and correct. 06.01.2025

Dienstleistungen · syfq nzm