Applying for approval for the early construction of an installation requiring a permit
Have you applied for a permit for an installation that requires approval? Then you can also apply to start construction of the system ahead of schedule.
-
Basic information
Have you applied for a permit for an installation that requires approval? If so, you can also apply to the competent authority for permission to begin construction of the facility ahead of schedule.
The competent authority can revoke the permit at any time. In addition, the approval may be subject to conditions or granted conditionally if you still have to meet certain requirements. The conditions are intended to ensure that the installation can be dismantled if it is not approved. To this end, the competent authority may require you to provide security. Collateral can be, for example, the deposit of money or securities as well as guarantees.
Requirements
- The competent authority must be able to adequately assess the impact of the planned installation from the application and the required documents.
- Your application must demonstrate a legitimate interest in the early start.
- As the applicant, you must undertake to compensate for all damage caused by the premature construction up to the time of the decision and, if the project is not approved, to restore it to its previous state.
-
Procedure
- In the application for approval, please indicate that you are also applying for approval for early commencement
- The competent authority will decide whether to approve the early start.
- You will receive a notice of approval or rejection.
Online application:
- Use the online service.
- Please log in with your access data via the Gemeinsam-Online service account or register first.
- ELiA-Online is a form-based online service that can also be used to attach additional documents (expert reports, drawings, etc.) to the application or notification using the upload function.
-
Necessary Documents
- ELiA forms
- (Electronic immission control application), available on the website of the Trade Supervisory Authority of the State of Bremen
- Required drawings, plans or expert opinions
- Explanatory notes on the system
- Other documents
- If necessary, ask the competent authority
- ELiA forms
-
Competent Department
-
Die Senatorin für Umwelt, Klima und Wissenschaft I Referat 23
- +49 421 361 2407
- An der Reeperbahn 2, 28217 Bremen
- Website
- office
@umwelt. bremen. de
-
Gewerbeaufsicht des Landes Bremen | Dienstort Bremen
- +49 421 361 6260
- Parkstraße 58-60, 28209 Bremen
- Website
- office
@gewerbeaufsicht. bremen. de - Legally secure e-communication more
-
Landesamt für Bergbau, Energie und Geologie
- +49 511 643 0
- Stilleweg 2, 30655 Hannover
- Website
- poststelle-
hannover @lbeg. niedersachsen. de
-
Gewerbeaufsicht des Landes Bremen | Dienstort Bremerhaven
- 0471 596132-70
- Lange Straße 119, 27580 Bremerhaven
- Website
- office
@gewerbeaufsicht. bremen. de
-
-
Online Services
-
ELiA-Online - Electronic application under immission control law
You would like to construct or modify an installation that requires a permit. Then you can create the necessary applications or notifications digitally here in the "ELiA-Online" online service and submit them to the responsible authority.
-
-
Fees / Costs
290,00 EUR bis 5.750,00 EUR
-
Deadlines & processing time
What deadlines must be paid attention to?
You must submit the application before you start building the system.
How long does it take to process
3 months bis 10 months The approval procedure is part of the licensing procedure.
This page has been automatically translated by DeepL. We cannot guarantee that the translation is correct.
The official information in German is complete and correct. 05.11.2025