Display the commissioning of a medium-sized combustion, gas turbine, and internal combustion engine plant
Are you planning to commission a medium-sized combustion plant, gas turbine, or internal combustion engine facility? If so, you must notify the relevant air pollution control authority.
-
Basic information
If you plan to commission a specific medium-sized combustion plant, gas turbine, or internal combustion engine, you must first notify the competent air pollution control authority.
The notification requirement generally applies to all combustion plants—whether or not they require a permit—with a thermal capacity of at least 1 MW and less than 50 MW.
For aggregated combustion plants, you must notify the authorities of the planned commissioning if the combined thermal output exceeds 1 MW and is less than 50 MW.
The information you provide will then be entered by the competent authority into a plant registry that is publicly accessible.
Requirements
You would like to commission a medium-sized combustion, gas turbine, or internal combustion engine plant.
-
Procedure
- Fill out the PDF form.
- You can find the link to the form under “Forms.”
- Send the completed form by email to the State of Bremen’s Trade Regulatory Authority.
- The responsible agency will process the notification and enter the reported facility into the facility registry.
- Once your notification has been received, the competent authority will inform you if you need to submit any additional documents for registration.
- The responsible authority will notify you as soon as the facility has been registered in the facility registry.
More information
- You are committing an administrative offense if you fail to submit the notification, or if you submit it incorrectly, incompletely, not in the prescribed manner, or not in a timely manner.
- Legal Remedy:
None. The administrative act is a final decision against which no legal remedy is available.
- Fill out the PDF form.
-
Necessary Documents
- Complete written or electronic notification
-
Forms
-
Fees / Costs
gebührenfrei
-
Deadlines & processing time
What deadlines must be paid attention to?
You must submit the notification before the intended commissioning of the facility.
How long does it take to process
1 month The registration period does not begin until the application, along with all necessary documents, has been received by the competent authority.