Report an emission-related change at a medium-sized combustion, gas turbine, or internal combustion engine facility
Do you want to make a change to a medium-sized combustion, gas turbine, or internal combustion engine facility that affects emissions? If so, you must notify the competent air pollution control authority.
-
Basic information
If you wish to make an emission-related modification to a medium-sized combustion, gas turbine, or internal combustion engine facility, you must first notify the competent air pollution control authority.
The notification requirement generally applies to all combustion plants—whether or not they require a permit—with a thermal capacity of at least 1 MW and less than 50 MW.
For aggregated combustion plants, you must notify the authority of the planned commissioning if the combined thermal output exceeds 1 MW but is less than 50 MW.
The authority responsible for your case will then enter the information you provide into a facility registry that is publicly accessible.
Requirements
You wish to make an emission-related modification to a medium-sized combustion, gas turbine, or internal combustion engine facility.
-
Procedure
- Fill out the PDF form.
- You can find the link to the form under “Forms.”
- Send the completed form by email to the State of Bremen’s Trade Regulatory Authority.
- The responsible agency will process the notification and enter the reported change into the equipment registry.
- Once your notification has been received, the responsible authority will inform you if you need to submit any additional documents for registration.
- The competent authority will notify you as soon as the change has been recorded in the facility registry.
More information
- You are committing an administrative offense if you fail to file the report, or if you file it incorrectly, incompletely, not in the prescribed manner, or not on time.
- Remedies:
None. The administrative act is a final act against which no appeal is possible.
- Fill out the PDF form.
-
Necessary Documents
- Complete written or electronic notification
-
Fees / Costs
gebührenfrei
-
Deadlines & processing time
What deadlines must be paid attention to?
Any change to a facility that affects emissions must be reported immediately, but no later than one month after the change occurs.
How long does it take to process
There is no deadline for processing.
This page has been automatically translated by DeepL. We cannot guarantee that the translation is correct.
The official information in German is complete and correct.
Updated on 24.08.2026