Send advance notice of a construction site
If you are planning a major construction project, you must notify the relevant health and safety authority in advance of setting up your construction site.
-
Basic information
If you are the owner of a construction site or have been given responsibility for a construction site, you must, under certain conditions, send an advance notice to the relevant health and safety authority at least 2 weeks before the construction site is set up. You must send advance notice if
- the expected duration of the work is more than 30 working days and more than 20 employees will be working on the construction site at the same time (i.e. over a period of at least one shift) or
- the scope of your construction work is expected to exceed 500 person-days (whereby one person-day comprises the work of one person over one shift).
Setting up the construction site begins with the essential preparatory work at the site of the construction project that is required immediately before it is carried out. This includes, for example
- Installation of social facilities: for example toilets, break rooms or washrooms,
- Installation of supply and disposal facilities,
- delivery of building materials, machinery and equipment.
You must also post the advance notice on the construction site on the first day of the construction site at the latest. Please note that
- the advance notice is clearly visible,
- the advance notice remains legible and unaffected by external influences and weather conditions,
- the advance notice is updated if there are significant changes. It is not necessary to resubmit it to the competent health and safety authority.
Significant changes that require the advance notice to be updated include, for example
- Clients or commissioned third parties change,
- Coordinator is newly appointed or changes,
- the duration of the construction work is shortened, which means that more work has to be carried out simultaneously or in unplanned shifts
- employees of several employers or subcontractors are working on the construction site at the same time for the first time,
- the number of people working on the construction site at the same time or the number of employers or companies without employees increases significantly.
Requirements
None.
-
Procedure
You must send the advance notification of a construction site in writing to the responsible office. You have the following options for this:
By online service
- Use the online service provided here.
- A service account is not required for this, you can use the online service directly.
- Fill it out completely and send it off.
By e-mail or by post
- Please use the application form provided under "Form".
- Download it and fill it out.
- Then send it to the relevant office by e-mail or post.
Note:
An informally submitted advance notice is legally permissible, provided it is complete. However, the use of the official form is strongly recommended.More information
You are in breach of regulations if you intentionally or negligently fail to provide the competent occupational health and safety authority with the necessary advance notice, or do not do so correctly, completely or in good time.
-
Necessary Documents
- Advance notice with the following minimum information:
- Location of the building site,
- Name and address of the client,
- Type of construction project,
- Name and address of the third party responsible instead of the client,
- name and address of the coordinator,
- expected start and expected duration of the work,
- expected maximum number of employees on the construction site,
- Number of employers and contractors without employees who are expected to work on the construction site,
- Details of the employers and contractors without employees already selected.
- Any other information you consider necessary.
- Advance notice with the following minimum information:
-
Competent Department
-
Gewerbeaufsicht des Landes Bremen | Dienstort Bremen
- +49 421 361 6260
- Parkstraße 58-60, 28209 Bremen
- Website
- office
@gewerbeaufsicht. bremen. de - Legally secure e-communication more
-
Gewerbeaufsicht des Landes Bremen | Dienstort Bremerhaven
- 0471 596132-70
- Lange Straße 119, 27580 Bremerhaven
- Website
- office
@gewerbeaufsicht. bremen. de
-
-
Online Services
-
Construction site announcement
Online service for advance notification in accordance with Section 2 (2) of the Ordinance on Safety and Health Protection on Construction Sites (Baustellenverordnung - BaustellenV). Such advance notice is required if the expected duration is more than 30 working days and the number of employees working simultaneously is more than 20 or the scope of the work is expected to exceed 500 person days (e.g. if 5 employees will be working for more than 100 days).
-
-
Fees / Costs
gebührenfrei
-
Deadlines & processing time
What deadlines must be paid attention to?
The advance notice must be sent at least 2 weeks before the construction site is set up.
How long does it take to process
Your advertisement will usually be reviewed shortly after receipt.
This page has been automatically translated by DeepL. We cannot guarantee that the translation is correct.
The official information in German is complete and correct. 16.04.2026