You want to erect cranes, mobile cranes, masts or other trades within the construction protection area of Bremen Airport?

  • Basic information

    The aviation authority is the body responsible for approving or authorizing the construction of an aviation obstacle in the construction protection area of Bremen Airport.

    Approval is required for all trades that exceed the heights subject to submission in the construction protection area so that air traffic is not endangered by the construction.

    If you erect plant, trees or equipment or create ground depressions, the safety of air traffic may be endangered. Therefore, under certain conditions, you need a permit from the responsible aviation authority. In the case of structural installations requiring a permit, this approval is granted as part of the building permit. For the erection of aeronautical obstructions (e.g. structures, equipment, construction cranes, also plantings [e.g. trees]) or the making of ground depressions for which you do not require a building permit, you submit the application directly to the responsible aviation authority.

    The height limits for the permit requirement result from the distance of the object to Bremen Airport and the height of the object in meters above ground and in meters above sea level. In the narrower construction protection area of Bremen Airport (1.5 km radius around the airfield reference point), all installations, excavations, trees and equipment are subject to approval regardless of their height.

    Exceptions apply in the eastern area of the airport city and in the area of the Schwäbisch Hall settlement. In some cases, approval is only required for heights of 18.2 m above sea level.

    Within a radius of 1.5 km to 4 km around the airport reference point, aviation obstructions are subject to approval from a height of 28.2 m NHN.

    An exception applies in parts of the new town and the old town. In some parts, approval is only required for heights of 48.2 m above sea level.

    Within a radius of 4 km to 6 km, the height requiring approval increases from 48.2 m NHN (4 km radius) to 103.2 m NHN (6 km radius).

    In the approach sectors, which extend east of the airport to Oyten and west to Ganderkesee, the height requiring approval increases from 3.2 m NHN (closest point to the airport) to up to 103.2 m NHN (10 km to 15 km from the airport).

    Outside the construction protection area of Bremen Airport on Bremen territory, aeronautical obstructions with a height of 100 m above ground are subject to approval.

    Information on the approval requirements for your project in Bremen, Bremerhaven and parts of Lower Saxony, which are located in the construction protection area of Bremen Airport, can be obtained from the Bremen Aviation Authority.

    Requirements

    • Fully completed application form
    • Site plan with location entry (preferably on a scale of 1:500 or 1:1000)
    • Crane data sheet (for tower cranes)
  • Procedure

    If the installation site is located in the construction protection area and the specified variable heights are penetrated, your request will be processed as quickly as possible on the basis of an application. Other authorities, such as DFS and BAF, will be involved in the procedure.

    The same applies to a height of 100 m above ground level on Bremen territory.

    If the heights subject to submission in the construction protection area and a height of 100 m above ground level outside Bremen territory are not exceeded, the applicant will be informed immediately that the aviation authority has no objections to the construction.

    Submit the application at least 2 weeks before the start of the project, but in compliance with the deadline regulation, so submit it as early as possible.

    Please state the type of obstacle, the location (location coordinates in UTM or WGS84) and the height in meters above ground level and, if known, in meters above mean sea level (NHN) of the top of the obstacle as well as the date of erection and, in the case of temporary obstacles, the duration until when the obstacle will be in place.

    The application form can be found under "Form".

    More information

    Please also check our website for more information.

  • Necessary Documents

    • Application form
    • Site plan with location entry

      if possible in scale 1:500 or 1:1000

    • Crane data sheet

      for tower cranes

  • Competent Department

    Contact Person

  • Forms

  • Fees / Costs

    105,00 EUR is the minimum fee. The fees of the aviation authority depend on the administrative effort of processing your application. Additional costs may be incurred due to the involvement of Deutsche Flugsicherung GmbH.

  • Deadlines & processing time

    What deadlines must be paid attention to?

    2 weeks at least

    How long does it take to process

    Usually 2 weeks.

  • Legal Bases

Feedback on quality

Your feedback will help us to identify and solve problems. You will not receive a personal response. Please do not submit any personal data.

Did you find what you were looking for?

How do you rate this page?*

*Mandatory field

This page has been automatically translated by DeepL. We cannot guarantee that the translation is correct.

The official information in German is complete and correct. 05.11.2025

Dienstleistungen · syfq nzm