Issue of a work permit


Procedure

The minimum lead times for the examination of the application in terms of time and content are

  • generally 2 weeks
  • 3 weeks for diversion measures
  • 6 weeks for modifications to light signal systems.

For the examination of the application

  • a fully completed application, and
  • approvable traffic sign plans / control plans and
  • Any necessary diversion plans

to be submitted.

More information

  • For general occupational health and safety, in particular protection of construction workers, as well as for the advance notice of construction sites > 30 working days and > 20 employees, or > 500 person days, the trade supervisory authority of the State of Bremen, Parkstraße 58/60, 28209 Bremen is responsible.