Procedure

Notify the building supervisory authority of the planned start of construction or the resumption of construction work after an interruption of more than three months at least one week in advance in text form.

The lower building supervisory authority will then check whether the conditions for starting the construction project are met. Feedback from the authority is not necessary.

Legal bases

More information

If the notification of the start of construction is not submitted or not submitted on time, this can be punished as an administrative offense in accordance with Section 83 (1) of the Bremen State Building Code.